    1. You are organizing an Annual Day in your university. Explain the steps to designing a project organization structure for this case. According to you which will be the most critical steps and why?
    2. India s Road and Transport Ministry has taken-up various Expressway Road Projects in the country. One of the such project consist of following parts
    Constructing roads
    Constructing tunnels
    Constructing bridges over the river
    Constructing flyovers and junctions
    Constructing convenient places (fuels stations, rest areas, etc.)
    Developing a solution for speed monitoring
    Finding suitable road material for areas in a heavy flood zone
    Using thing information as example, describe various project life cycle models

    3. A project manager is struggling to manage the project due to risk and the cost. The details are
    Original Project Budget: Rs. 40, 00,000
    Original Estimated Duration: 36 Months
    Elapsed Time: 12 Months
    Money Spent till Date: Rs. 15,00,000
    Work Completed: 40 %
    Risk Identified and Ratings

    a. Suggest the risk priority to this project manager.
    b. Find out the Estimate at Completion using all possible ways.

    For Nmims answersheets contact
    [email protected]
    +91 95030-94040

     

    Donut Charts Tableau

    Context Filters in Tableau

    R T G CRANE COURSE R T G LICENCE IN BANGALORE INDIA

    OFFSHORE CRANE TRAINING INSTITUTE IN BANGALORE INDIA